Originally published in the Seattle Post-Intelligencer, December 26, 1900

A Christmas Day event

Reports of tests received at city hall by telephone—Two weeks more will elapse before water is turned into the reservoirs—Assistant City Engineer Scott makes good his predictions

The Landsburg dam is used to divert drinking water from the Cedar River to the pipeline serving the City of Seattle. The original dam was constructed in 1900 and updated in 1935, as shown here. (From Black Diamond NOW.)

The Landsburg dam is used to divert drinking water from the Cedar River to the pipeline serving the City of Seattle. The original dam was constructed in 1900 and updated in 1935, as shown here. (From Black Diamond NOW.)

Cedar River water flowed into the city limits of Seattle Monday night at 10 o’clock through the mains of the new gravity system. Unknown to the general public the water from the river was let into the main pipe line filling it almost to its greatest capacity and was then allowed to flow into the main trunk sewer at Twelfth Avenue South and Lane Street, by which it found its way into Elliott Bay.

Twelve days ago Assistant City Engineer Scott , who has charge of the work on the pipe line and at the intake on the river decided if possible to carry out the prediction he made six months ago that water from Cedar River would flow into the city limits on Christmas day, 1900. (more…)